National Grid ESO has unveiled a proposal to connect 4.5GW of clean power in the Celtic Sea.
It has published Beyond 2030: Celtic Sea, setting out a recommended design to connect up to 4.5GW of floating offshore wind capacity – enough to power more than 4 million homes. This design would see 3GW connected into two locations in South Wales, along with a further 1.5GW connected into the South West of England.
Each proposed offshore wind farm will have its own connection to the onshore electricity network – one being a high voltage direct current (HVDC) connection into a potential new South Wales Connection Node, along with two connections that use high voltage alternating current (HVAC) technology into Carmarthenshire and North Devon.
A number of designs were assessed against their impact on local communities and the environment, the cost to the consumer, deliverability and operability. The chosen design would have no need for new overhead lines to connect the offshore wind, meaning less impact on the environment and community than others considered, and make use of current wider transmission infrastructure compared to the other options.
The chosen design also comes in regions with an already identified need for a substation or an already-proposed substation, such as Carmarthenshire and North Devon. Aligning with other infrastructure needs has the potential for a more coordinated approach to locating new substations.
The proposals will enable The Crown Estate’s Celtic Sea Floating Offshore Wind Leasing Round 5, which is targeting 4.5GW of floating offshore wind power and could create 5,300 permanent jobs during the construction phase of projects, while driving up to £1.4 billion of economic activity.